(1) The tower crane driver and signal personnel must be specially trained and issued a certificate by the relevant department, and pay attention to whether the tower type learned by the driver is consistent with the actual tower type.
(2) Special personnel and special plane management, captain responsibility system, and strict handover system.
(3) For newly installed or overhauled tower cranes, the whole machine must be tested in accordance with the instructions.
(4) The tower crane should maintain a safe distance from the overhead transmission line.
(5) Appropriate fire extinguishing equipment should be equipped in the driver's cabin.