The correct maintenance of the hoist is vital to reduce the failure rate of the machine and extend the service life of the machine.
In addition to daily maintenance, regular maintenance should be carried out according to the following procedures:

Time interval

Parts

Explanation

40 hours of work - no matter the time

At least once a month

1. Anti-fall safety device

If the safety without file or running any abnormal sound, should be down to check, sent to the factory inspection

2Signboard

Ensure that all the signboards on the machine are clear and complete

3Reducer

The lubricating oil has leakage - check the decelerator oil level and add the lubricating oil when necessary

4Roller and back wheel

Ensure that all bolt connections are fastened and no loose

5Drive plate

Ensure that all bolt connections are strong and not loose

6Motor brake

Ensure that the gap between the fixed plate and the rotating disc is not less than 0.5mm, and the brake disc is replaced when necessary.

7.Braking distance

When the suspension cage is fully loaded, the braking distance is not more than 0.35m

8.Electrical system

Check whether the connection posts and contactors are loose

9Cable

Check whether the cable is wearing or distorting

10Rack

Toothed grease

100 working hours

- no matter the time

At least 6 times a year

11.Connecting bolts for standard section

Check whether there is a loose phenomenon, timely and solid

12Attaching bolt

Check whether there is a loose phenomenon, timely and solid

13Limit, limit switch and its collision block

Check whether the switch is flexible or whether each block is moved or not.

14Cable guide device

Check whether the cable arm passes smoothly or not, the guide frame is fixed

Is it reliable, rubber wear

15Gear, rack

Inspection of wear and tear according to "wear and adjustment limit"

16.Lubrication interval time

According to the requirements to lubricate

400 working hours

- no matter the time

At least 4 times a year

17Roller

Check the clearance and wear of the roller and the column tube

18Safety device

According to the requirement to do falling test

19Motor

Refer to the introduction of the "motor" section

1000 hours of work - no matter the time

At least 1 times a year

20Couplet rubber block

Check the extrusion and wear of rubber block

21.Lubrication interval time

See the "lubrication list"

22Corrosion and wear

To check the whole equipment, the corresponding protection measures must be taken for the frequently corroded parts.